15000 SF Data Center

Project Manager while with Mashburn Construction of the Design-Build construction of this 15,000 SF state of the art hurricane-proof and earthquake-proof data center.  This concrete tilt-up project included redundant electrical systems, a 4,000 SF raised data floor system, specialized HVAC for the highly technical data and power requirements as well as an integrated access and security system.  This team effort resulted in a fast track completion of the project in less than 5 months.

North Charleston, SC